Hospital Asbestos Removal
Barnsley
Brief
We received an enquiry from a hospital to deal with their issues of Asbestos in three of their theatres. This was part of the hospitals refurbishment plans.
We won this contract due to our high standards in Health and safety and our competitive pricing.
This project required 3 phases, with a time frame of around 18 days on each phase.
Due to the nature of this building, we had to manage the general public and the hospital workers, creating a safe corridor for a walkway. We constantly monitored this route to ensure it was non-toxic, no dust and keeping it sterile.
We ensured there were no disruptions throughout the area covered in each phase, our team worked extremely hard to keep this important workplace to the standard required.
While on-site there had been a random inspection from the Health and Safety Executive as well as an external audit from ACAD.
This had been carried out during the 2nd phase, which resulted in an excellent audit score.
Our 98% Audit is something we pride ourselves on.
We are now entering phase three of this asbestos removal project.