An Old Mill

Nottingham

Brief

We received an enquiry from an old mill site as building work was underway.

An asbestos refurbishment survey had been carried out and asbestos insulation debris was found to the floor area in the boiler room following the boiler removal.

We successfully won the contract to carry out an environmental clean of the boiler room.

Solution / Action Taken

ICE Asbestos work to conditions set out under our asbestos licence, issued by the Health and Safety Executive to ensure that we control the asbestos fibre release during our works

This was a relatively small job, taking around 3 days, but we still adhere to strict guidelines to ensure that our work is carried out to the highest safety standards under fully controlled conditions, under negative pressure

On the first day we set up the work area, using direct connection to an operating decontamination unit to prevent the transiting of operatives on site

The asbestos installation debris was found in the soil to the floor, therefore we had to remove all contaminated soil down to the brick below. This was carried out by wetting the contaminated soil and shovelling the waste into asbestos waste bags

The waste was transited through the bag lock to the segregated waste vehicle, which was parked alongside the decontamination unit

Following the floor clearance, the walls were sprayed with a diluted surfactant and wire brushed to ensure there was no debris present

The floor area then had a final clean before the enclosure was handed over to the independent analyst for a thorough four stage clearance

Once the air clearance was issued the work area was deconstructed and the building was handed over to the Client 

Get in touch with
our experts, today!

Click Here
Cookies

This website uses cookies. Please let us know if you agree to the use of these cookies :
I Accept I Decline

Privacy Policy | 3rd Party Data Processors | Disable Cookies
Cookies